 We undertake a variety of earthwork contracts including on-site cut and fill, off-site bulk earthworks, importation of fill materials, site clearance and land restoration. Our competitive strength derives from owning our own operated plant and tipper fleet, and by the employment of experienced technical and managerial resources.
Detailed below are a selection of contracts we have sucessfully undertaken which illustrates the nature and diversity of the work we are capable of carrying out.
HOUSING, LEICESTER| Client | House Builder | | Acting as ... | Contractor | | Start date | March 2006 | | Value, Łk | 143 | | Duration, wks | 5 | | Volume, m3 | 11,500 |
Load cart & tip of inert subsoils from stockpile.
SCHOOL, LEICESTER
| Client | Groundworks Contractor | | Acting as ... | Contractor | | Start date | January 2006 | | Value, Łk | 30 | | Duration, wks | 2 | | Volume, m3 | 2,000 | Reduced level excavation and removal of inert soils for the construction of a school extension.
CAR PARK, WEST BRIDGFORD | Client | Highways Authority | | Acting as ... | Contractor | | Start date | September 2005 | | Value, Łk | 43 | | Duration, wks | 2 | | Volume, m3 | 650 |
Reduced level excavation and removal of contaminated and inert soils for the construction of a municipal car park.
LAND REMEDIATION, NOTTINGHAM
| Client | House Builder | | Acting as ... | Principal Contractor | | Start date | July 2004 | | Value, Łk | 125 | | Duration, wks | 1 | | Volume, m3; | 1,650 |
Reduced level excavation and removal of hazardous and contaminated soils for land development.
REINFORCED EARTH NOISE BUND, OAKHAM
| Client | House Builders | | Acting as ... | Contractor | | Start date | March 2004 | | Value, Łk | 108 | | Duration, wks | 8 | | Volume, m3 | 2,500 |
A technically difficult contract involving the construction of a narrow width geogrid reinforced earth bund with steep sides. Restricted site access and the construction and tie-in of a log retaining wall and modular block wall added to the complexity of the project. |